Question: 1. A project with three tasks A,B,C; and a duration of a two full weeks- 7 days each. A designer and a programmer are needed

1. A project with three tasks A,B,C; and a duration of a two full weeks- 7 days each. A designer and a programmer are needed to work on the project for the full duration. The designer costs $20 per day while the programmer costs $10 per day. Calculate the total cost of the designer and the programmer during the two weeks duration? (show all the steps required to solve it) [1] (2 points) Enter your