Question: 1. a. Refer to the table below. What is the cumulative budgeted cost at the end of week 6? Amounts are in thousands of dollars.

1. a. Refer to the table below. What is the

1. a. Refer to the table below. What is the cumulative budgeted cost at the end of week 6? Amounts are in thousands of dollars. 30 10 15 70 10 10 10 20 10 10 40 5 Task 1 Task 2 Task Task 4 Total Cumulative 30 170 10 25 15 10 25 1 > 10 5 20 The cumulative budgeted cost at the end of week 6 is $100,000. b. Below is a table of actual costs. What is the cumulative actual cost at the end of week 6? Determine whether there is a cost overrun or underrun. What is causing it? Amounts are in thousands of dollars. Week 1 2 3 56 10 16 168 10 10 12 24 12 Task 1 Task 2 Task 3 Task 4 Total 10 26 18 12 29 17 Cumulative Amounts are in thousands of dollars. c. Below is a table of the cumulative percentages of work completed by the end of week 6. What is the cumulative earned value of the project at the end of week 6? Is it good? Week 3 5 6 Task 1 30 80 100 10 Task 2 2535 55 65 Task 3 1020 Task 4 Amounts are cumulative percent complete. d. What is the CPI at the end of week 6? What is the CV? e. Calculate the FCAC using the first two methods described

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!