Question: 1 . A specific product has demand during lead time of 3 5 0 units, with a standard deviation during lead time of 8 0
A specific product has demand during lead time of units, with a standard deviation during lead time of units. Management wants a service level.
a What value of Z should be applied?
b How many units should be carried as safety stock?
c What is the appropriate reorder point?