Question: 1. According to an outside article we read, when interpreting the results of the weighted scoring model of project selection, if the difference between the
1. According to an outside article we read, when interpreting the results of the weighted scoring model of project selection, if the difference between the project options returns relatively small values, then:
Select one:
a. The options are essentially the same.
b. We need to further study the project options.
c. The differences are of more significance than are the actual scores.
d. All of the options are correct
2.
Which of the following is a true statement about project selection?
Select one:
a.A longer payback period usually means a less lucrative investment.
b.A shorter period recoups the money more quickly.
c.All other things being equal, a project with a shorter payback period generally is seen as more desirable
d.All of the above
e.Only B and C
3. According to statistics provided in a lecture, one in ______ projects saw a budget overrun of 200%?
Select one:
a.Three
b.Four
c.Six
d.Ten
4.
Measuring project progress against expected goals takes place in the ________ lifecycle phase.
Select one:
a.Initiating
b.Planning
c.Executing
d.None of these