Question: 1 Additional Problem 1 6 - 1 ( Algo ) 3 points References A bank recelves load applications from 6 customers a day. The bank

1
Additional Problem 16-1(Algo)
3 points
References
A bank recelves load applications from 6 customers a day. The bank has promised customers that applications will be processed in the order they are recelved. The table below shows the applications in the order they were recelved, the processing time for each loan application, and the due date that customers need to hear about their application status:
\table[[Customer,\table[[Processing],[time--(days)]],\table[[Due date],[(days)]]],[A,7,10],[B,9,15],[C,6,8],[D,5,10],[E,8,19],[F,10,25]]
a. Determine the average processing time for applications, the average days tardy for each customer's application, and the average number of applications being processed if the bank processes the applications in the order they were received.
Note: Round your answers to 2 decimal places.
\table[[Average flow time,25.33,days],[Average tardiness,11.33,days],[Average number of jobs,3.38,applications]]
b. The bank decides to improve their application processing performance by giving priority to the loans that take a shorter time to be processed (SPT). If they do this, determine the average processing time, average tardiness, and the average number of applications processed.
Note: Round your answers to 2 decimal places.
\table[[Average flow time,23.33,days],[Average tardiness,9.67,days],[Average number of jobs,3.11,applications]]
c. Now assume the bank gives priority to the applications who have the earliest due dates (EDD). Determine the average processing time, average tardiness, and average number of applications in this scenario.
Note: Round your answers to 2 decimal places.
\table[[Average flow time,23.67,days],[Average tardiness,,days],[Average number of jobs,3.16,applications]]
d. Now assume the bank accounces that it will take into account both the processing time and the due dates in ordec to determine the order of the applications to be processed (CR). Calculate the average processing time, average tardiness, and average number of applications.
Note: Round your answers to 2 decimal places.
\table[[Average flow time,,days],[Average tardiness,,days],[Average number of jobs,,],[applications,,]]
 1 Additional Problem 16-1(Algo) 3 points References A bank recelves load

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!