Question: 1) Agile techniques are most useful when the how to do this for the task(s) is not yet fully ____________.* 2) Most companies have a

1) Agile techniques are most useful when the "how to do this" for the task(s) is not yet fully ____________.*

2) Most companies have a permanent management committee reviewing project successes and failures to help the company improve return on investment (ROI).*

1 point

True

False

3) [Checkbox: 1 to 4 options may be needed]: The project manager's final report to the sponsor should include:*

Criticism of the users who kept asking for more scope changes

Evaluation of how good the people from contracting or consulting firms were

A recounting of problems during the project

Praise for special efforts and contributions made by employees

4) [Checkbox question: the correct answer is formed by selecting 1 to 4 of the options] Why does the Project Management Institute think IT projects are so much more difficult than other types of project?*

Most business people try to avoid making technology-related decisions

It's actually quite difficult to turn a complicated business problem into an algorithm that is programmable.

Actually, they're not more difficult: IT people just make lousy project managers

Coding and testing take up most of the time, are hard to plan in detail, and are subject to excessive scope creep and rework.

5) A good project managerprovides line managers with an email concerning performance evaluation input for each of their employees on the project team.*

1 point

True

False

6) Project business cases can just the raw numbers. Doing all those present value (PV) calculations is just unnecessary work.*

1 point

True

False

7) What is the difference between effort and durations?*

1 point

Effort tells you if more than one person is required, duration tells you how much time is left before the task will be finished.

Effort the the number of hours of work the tasks requires, duration is the number of days you plan for this task to take.

Effort is the amount of work one person can do on an average day, duration is how long they havre to do it in.

Effort tells you if overtime will be required, duration tells you how long you have to get the work finished.

note - in checkpox question, u can select more than 1 answers

plz send asap.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!