Question: 1- Ahmed is looking at a document that outlines the specific deliverables and sub deliverables required to complete the writing of a technical support manual.
1-
Ahmed is looking at a document that outlines the specific deliverables and sub deliverables required to complete the writing of a technical support manual. He is most likely viewing the?
a.
Process Breakdown structure
b.
Work Breakdown Structure
c.
Work Structure
2-
In reviewing the project plan, Ahmed sees that the first prototype must be completed by October 15. This would be classified as a
a.
Objective
b.
Constraint
c.
Milestone
3-
To construct a high quality, custom home within five months at costs not to exceed BD150,000 is best classified as
a.
Milestone
b.
Objective
c.
Constraint
4-
After reviewing the project scope statement, Osama specifies that costs must stay within BD300,000. This criterion is classified as
a.
Constraint
b.
Objective
c.
Milestone
5-
The ------------------is used to assist in making project trade-offs among schedule, costs and performance objectives.
a.
project priority matrix
b.
project matrix
c.
Mileston priority matrix
6-
The lowest element in the hierarchical breakdown of the WBS is
a.
a work objective
b.
a work package
c.
a work scope
7-
The highest element in the hierarchical breakdown of the WBS is
a.
the project
b.
the element
c.
the management
8-
The integration of the lowest level of the WBS with the organization units responsible for performing the work is known as
a.
Organizational Breakdown Structure
b.
Manager Breakdown Structure
c.
Organizational Structure
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock