Question: 1. Also known as total float, total ______ is the total amount of time that a task may be delayed without delaying the project end
1. Also known as total float, total ______ is the total amount of time that a task may be delayed without delaying the project end date.
A. delay
B. fill
C. slack
D. lead
2. The ______ cost and duration estimation technique starts at the lowest level of detail in the WBS. For each low-level task, a work content estimate is prepared based on the nature of the individual task. These individual task estimates are aggregated into the overall project estimate.
A. top-down
B. bottom-up
C. parametric
D. template
3. ______ is a task on which a subsequent (following) task depends in a project schedule.
A. Successor
B. Precedence relations
C. Predecessor
D. Precedence constrains