Question: 1) ____ are generated by the priority planning system and involve the translation of the priorities, generally given in units of product or some common
1) ____ are generated by the priority planning system and involve the translation of the priorities, generally given in units of product or some common unit, into hours of work required at each work center in each time period:
Select one: a. Capacity bills b. Work center reports c. Capacity requirements d. Production activity control
2)
An order for 100 of a product is processed on operation A. The setup time is 50 minutes and, the run time per piece is 9 minutes. Since this is a rush order, it can be split into two lots of 50 each and run on two machines in the work center. The machines can be set up simultaneously.
1. The total manufacturing lead time is ................... minutes if 100 units are run on one machine.
2. The total manufacturing lead time is ...................... minutes when100 units are run on two machines simultaneously.
3. The total manufacturing lead time is ..................... minutes if the second machine cannot be set up until the set up on the first machine is completed.
3)
A pull system is developed to provide which of the following?
Select one: a. only used when demand is constant and known b. to provide only what is needed and when it is needed c. an alternative to a classic MRP system
4)
Which system extends MRP II to tie in customers and suppliers?
Select one: a. JIT b. ERP c. IRP d. Enhanced MRP II e. MRP III