Question: 1. Assume you are a software project manager and that youve been asked to develop a network diagram for the project. (1)Draw a network diagram

1. Assume you are a software project manager and that youve been asked to develop a network diagram for the project. (1)Draw a network diagram for this project and calculate the earliest start time/ latest start time for each activity. (2)Identify the critical path from the network diagram.

Activity precedence chart

No

Activities

Duration

Previous activities

A

Preparation

1

-----

B

Design of the automated warehouse

3

A

C

Construction of the warehouse building

10

A

D

Development of the control system

8

B

E

Provision of the mechanical devices

4

B

F

Component test of control system parts affecting the warehouse building

6

C, D

G

Component test of control system parts affecting the mechanical devices

10

D, E

H

Installation of control system parts

4

F

I

Integration test, system test and introduction

5

F, G, H

(1) Network Diagram (5 points)

(2) Earliest Start/ Earliest Finish/ Slack time (3 points)

Activities

Earliest Start

Latest Start

Slack time

A

B

C

D

E

F

G

H

I

(3) Critical Path(s) (2points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!