Question: 1. Assume you are a software project manager and that youve been asked to develop a network diagram for the project. (1)Draw a network diagram
1. Assume you are a software project manager and that youve been asked to develop a network diagram for the project. (1)Draw a network diagram for this project and calculate the earliest start time/ latest start time for each activity. (2)Identify the critical path from the network diagram.
Activity precedence chart
| No | Activities | Duration | Previous activities |
| A | Preparation | 1 | ----- |
| B | Design of the automated warehouse | 3 | A |
| C | Construction of the warehouse building | 10 | A |
| D | Development of the control system | 8 | B |
| E | Provision of the mechanical devices | 4 | B |
| F | Component test of control system parts affecting the warehouse building | 6 | C, D |
| G | Component test of control system parts affecting the mechanical devices | 10 | D, E |
| H | Installation of control system parts | 4 | F |
| I | Integration test, system test and introduction | 5 | F, G, H |
(1) Network Diagram (5 points)
(2) Earliest Start/ Earliest Finish/ Slack time (3 points)
| Activities | Earliest Start | Latest Start | Slack time |
| A |
|
|
|
| B |
|
|
|
| C |
|
|
|
| D |
|
|
|
| E |
|
|
|
| F |
|
|
|
| G |
|
|
|
| H |
|
|
|
| I |
|
|
|
(3) Critical Path(s) (2points)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
