Question: 1 . Assuming two phase ( 2 green phases only ) control, compute critical lane flows for the two phases. Use the left turn equivalence
Assuming two phase green phases only control, compute critical lane flows for the
two phases. Use the left turn equivalence factor of even though protected left turn phases are not provided.
Compute clearance intervals for both green phases using the new ITE method, round your computed values up to the next higher second.
Use Webster's equation to estimate the cycle length. Instead of using the HCM "default" saturation flow of assume we have measured the saturation flow value and it is
Estimate green times for the two phases.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock