Question: 1. Based on the productivity below, the team size that is the most productive is a team size of _________ people. Team Size Output (units)
1.
Based on the productivity below, the team size that is the most productive is a team size of _________ people.
Team Size Output (units)
4 1300
2 650
3 1020
4 1200
2 720
3 1000
3. The previous forecast of 105 turned out to be four units less than actual demand. The next forecast is 125. Using simple exponential smoothing, the value of alpha is _________.
4.
Using the least squares trend line for the following data, the forecast for Period 5 is _________ units.
Year Units
Period 0 900
Period 1 700
Period 2 600
Period 3 400
Period 4 200
5.
Octobers forecast using the naive approach and the following data is _________ units.
Month Units
April 100
May 150
June 90
July 170
August 110
September 190
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts