Question: 1. Calculate the average waiting time. For the given process using Round Robin scheduling with a time quantum of 4 units P1 P2 P3

1. Calculate the average waiting time. For the given process using Round Robin scheduling with a time quantum

1. Calculate the average waiting time. For the given process using Round Robin scheduling with a time quantum of 4 units P1 P2 P3 Process ID P4 1 Process Id P5 2 3 4 5 6 Arrival Time 0 1 2 3 4 6 2. Consider the set of 5 processes whose arrival time and burst time are given below- Arrival time 0 1 2 3 Burst Time 4 5 6 3 1 5 4 Burst time 5 3 1 2 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

i Initialize the time Start at time t 0 Execute processes using Round Robin Process 1 Arrival Time 0 Burst Time 5 Execute for 4 units Quantum Time Rem... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Programming Questions!