Question: 1. Calculate the net present value for each project from the following cash flows, and state whether each project should be undertaken and why or
1. Calculate the net present value for each project from the following cash flows, and state whether each project should be undertaken and why or why not: Original Investment Year 1 Year 2 Year 3 Year 4 Interest rate IA IB (60.000.00) (35,000.00) 13.000.00 14,000.00 15,000.00 15,000.00 17.000.00 10,000.00 22,000.00 5,000.00 12% 8% Net Present Value Undertake Project? Discuss, very briefly using the net present value criteria, why or why not. 1A 1B