Question: 1. Check whether the Earliest Due Date (EDD) algorithm produces a feasible schedule for the following task set (all tasks are synchronous and start at

1. Check whether the Earliest Due Date (EDD) algorithm produces a feasible schedule for the following task set (all tasks are synchronous and start at time t=0): Ji J2 J3 | J4 Ci 4 5 2 3 Di 9 16 10 UN