Question: 1. Complete the table and indicate the critical path. Activity A BUDE C F G ABCDEFGH A 3 500 700 400 300 250 600
1. Complete the table and indicate the critical path. Activity A BUDE C F G ABCDEFGH A 3 500 700 400 300 250 600 900 Time Earliest Est Start 3 7 Activity Cost per/day Available days H 1000 9 3 2 B 3 6 2 3 2 Earliest Finish F H 2. Crash the above project using the following information. Indirect costs per day equal $1400. How much money can the firm save? Activity Cost Savings C.P. E 7 G Latest Start Name 6 3 Latest Finish H 2 Slack
Step by Step Solution
There are 3 Steps involved in it
Table Completed Activity Time Est Earliest Start Earliest Finish Latest Start Latest Finish Slack A ... View full answer