Question: 1. Complete WBS by adding task. 2 determine work pkgs. 3.Dwvelop activity for each PKG. Activity Activity Time (Work Weeks) 1 Customized Connecting Software Preceding

1. Complete WBS by adding task. 2 determine work

1. Complete WBS by adding task. 2 determine work pkgs. 3.Dwvelop activity for each PKG.

Activity Activity Time (Work Weeks) 1 Customized Connecting Software Preceding Task Activity Connecting Software Project for Mrs. Y None Requirement Collection None Resource Allocation 2 Hardware Specification 2 Software Build 3 2 10 3 4 4 4 5 10 6 4 2 7 3,9 1 8 6 2 Unit Testing IPR Filing System Testing End to End Testing Project Handover END (Milestone) 9 5 5 10 7,9 4 11 10 0 Customized Connecting Software Project Requirement Collection Resource Allocation Hardware and Software Built End of Testing Handover

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!