Question: 1. Compute the IRR statistic for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final

1. Compute the IRR statistic for Project E. The appropriate cost of capital is 8 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project E
Time: 0 1 2 3 4 5
Cash flow: $1,000 $350 $480 $520 $300 $100

2. Compute the MIRR statistic for Project I if the appropriate cost of capital is 12 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)

Project I
Time: 0 1 2 3 4
Cash flow: $11,000 $5,330 $4,180 $1,520 $2,000