Question: 1. Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign.
1. Compute the NPV for Project M if the appropriate cost of capital is 8 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)
| Project M | ||||||
| Time: | 0 | 1 | 2 | 3 | 4 | 5 |
| Cash flow: | −$1,600 | $470 | $600 | $640 | $720 | $220 |
Should the project be accepted or rejected?
Step by Step Solution
3.31 Rating (154 Votes )
There are 3 Steps involved in it
NPV R 8 100 008 470 1008 R R 11 1i 1i 600 1008 640 1008 Time 0 1 2 3 ... View full answer