Question: 1) Consider the AoN network given below with associated activities and activity times given on nodes for a CPM project B(9) D(3) A(6) C(12) E(10)

1) Consider the AoN network given below with

1) Consider the AoN network given below with associated activities and activity times given on nodes for a CPM project B(9) D(3) A(6) C(12) E(10) a. Find earliest start times, earliest finish times, latest start times and latest finish times of activities. b. Find the slack times of activities and specify critical activities. 2) Consider the AoN network given below with associated activities and activity times given on nodes for a CPM project . Define your decision variables and write an LP model in open mathematical form to find minimum project completion time.( B(7) D(3) A(5) C(2) E(4)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!