Question: 1. Construct a network for this problem. Using AOA and AON. 2. Determine the expected time and variance for each activity. 3. Determine ES, EF,

1. Construct a network for this problem. Using

1. Construct a network for this problem. Using AOA and AON.

2. Determine the expected time and variance for each activity. 3. Determine ES, EF, LS, LF, and slack time for each activity. 4. Determine the critical path(s) and project completion time.

WITHOUT USING EXCEL

Preceding a b none 4 0 0 3 2 A-B A-B 10 24 16 10 12 A-B 4 10 3 1. Activity Description A-B Feasibility study B-C Acquire site B-D Prepare plans B-F Marketing strategy C-D Soil test D-E Legal approvals D-F Loan application E-F Evidence approval E-G Obtain bids F-G Secure financing G-H Release contract 6 30 2 B-C C-D & B-D C-D & B-D D-E D-E D-F, B-F, E-F E-G & F-G N O O O W 00 N 01 4 0 O CON N 6 12 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!