Complete Earned Value Management Formulas You are the project manager of the Divell Project for your...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Complete Earned Value Management Formulas You are the project manager of the Divell Project for your company. This project is scheduled to last 18 months and has a budget at completion of $1,500,000. The project is currently 30 percent complete, though you were supposed to be 35 percent complete at this time. Due to some unforeseen errors, your project has been delayed and you've spent $485,230. (10 points) 1. Given this information, complete the following table of earned value management formulas: Name Actual Costs (AC) Planned Value Earned Value Cost Variance Schedule Variance Cost Performance Index Schedule performance index Estimate at completion Estimate to complete To-complete performance index (BAC) To-complete performance index (EAC) Variance at completion Formula Actual monies spent PV-percent complete of where the project should be EV-percent complete x budget at completion CV-EV-AC SV EV-PV CPI-EV/AC SPI-EV/PV EAC BAC/CPI ETC-EAC-AC (BAC-EV)/(BAC-AC) (BAC-EV)/(EAC-AC) VAC-BAC EAC Formula Result 2. A project has a BAC of $250,000 and is supposed to be 50 percent complete, but the project is only 40 percent complete. The project manager on this project has spent $145,000 due to some errors in the project work. What is this project's estimate to complete? (5 points) 3. A project has a BAC of $250,000 and is supposed to be 50 percent complete, but the project is only 40 percent complete. The project manager on this project has spent $145,000 due to some errors in the project work. What is this project's variance at completion? (5 points) Complete Earned Value Management Formulas You are the project manager of the Divell Project for your company. This project is scheduled to last 18 months and has a budget at completion of $1,500,000. The project is currently 30 percent complete, though you were supposed to be 35 percent complete at this time. Due to some unforeseen errors, your project has been delayed and you've spent $485,230. (10 points) 1. Given this information, complete the following table of earned value management formulas: Name Actual Costs (AC) Planned Value Earned Value Cost Variance Schedule Variance Cost Performance Index Schedule performance index Estimate at completion Estimate to complete To-complete performance index (BAC) To-complete performance index (EAC) Variance at completion Formula Actual monies spent PV-percent complete of where the project should be EV-percent complete x budget at completion CV-EV-AC SV EV-PV CPI-EV/AC SPI-EV/PV EAC BAC/CPI ETC-EAC-AC (BAC-EV)/(BAC-AC) (BAC-EV)/(EAC-AC) VAC-BAC EAC Formula Result 2. A project has a BAC of $250,000 and is supposed to be 50 percent complete, but the project is only 40 percent complete. The project manager on this project has spent $145,000 due to some errors in the project work. What is this project's estimate to complete? (5 points) 3. A project has a BAC of $250,000 and is supposed to be 50 percent complete, but the project is only 40 percent complete. The project manager on this project has spent $145,000 due to some errors in the project work. What is this project's variance at completion? (5 points)
Expert Answer:
Answer rating: 100% (QA)
Answer 1 Actual Costs AC485230 Planned Value450000 Earned Val... View the full answer
Posted Date:
Students also viewed these finance questions
-
Construct the energy-level diagram for the He+ ion (See Fig 27-27).
-
How are quantitative and qualitative data analysis different?
-
The figure shows a schematic diagram of a defective eye. What is this defect called?
-
EBIT $ 600,000 g 0.0% r 10.0% Shares o/s 200,000 Taxes 25.0% NI $ 450,000 Before Recapitalization: Value of Ops $ 4,500,000 Value per share $ 22.50 EPS $ 2.25 1:13 sthn 1h dialexh Recap: New debt...
-
Explain the various root causes of management resistance to empowerment.
-
The local community feels that secondary school education is a necessity in our society and that lack of education leads to a number of social problems. As a result, the local school board has...
-
A U.S. Treasury bond pays a 7% coupon on January 7 and July 7. How much interest accrues per \($100\) of principal to the bond holder between July 7, 2013, and August 9, 2013? How would your answer...
-
Statement of Legal Debt Margin. In preparation for a proposed bond sale, the city manager of the City of Appleton requested that you prepare a statement of legal debt margin for the city as of...
-
Who developed the relational model, when, and why?
-
The case study shown below provides an overview of Road Transit Systems (RTS) - a specialist preventative vehicle maintenance program operator in NSW, Australia. A number of attributes have been...
-
Part 1: Preparation Of A Volumetric Stock Solution Mass of methylene blue (g) 0.713 Volume of stock solution (mL) 100.0
-
Assume that the auditor has examined the supporting documentation for additions to property, plant and equipment and found a net monetary overstatement in the sample. The relevant information is...
-
The CFO of your company has asked for your support in preparing a report for the business's board of directors. Many of the board members are new, and some of them have little background in finance....
-
Consider the following matrices: 3 2 6 1 1 -3 A = -6 3 2 and B = 0 -4 2 6 -3 -3 -4 -2 1.1 Use the definition below to determine whether the matrix A = A is orthogonal. Definition: A matrix is...
-
Suppose the following were the gross profit margins for Green Mountain Coffee Roasters (GMCR) from 2011 through 2013. 2011: 34.13% 2012: 32.89% 2013: 37.16% What could be an explanation of the...
-
A company pays $1200 plus 8% tax for a one-year insurance policy on June 1, 2021. How much is its insurance expense for the year ended December 31, 2021? Enter your answer without $ signs, decimal...
-
What are the specific strategies or advice from the networking activities that have been particularly helpful in navigating the career path in pursuing a career in healthcare administration?
-
If there is an unrealized holding gain on available-for-sale investments, it is reported as?
-
Which of the following types of epigenetic changes may promote cancer? a. DNA methylation b. Covalent modification of histones c. Chromatin remodeling d. All of the above may promote cancer.
-
The underlying cause(s) of epigenetic changes associated with cancer may be a. mutations in genes that encode chromatin-modifying proteins. b. environmental agents that alter the function of...
-
Normal (nonmutant) tumor-suppressor genes often function a. as negative regulators of cell division. b. in the maintenance of genome integrity. c. in the stimulation of cell division. d. as both a...
Study smarter with the SolutionInn App