Question: 1. Construct the appropriate control chart for the 11 observations, and determine if the process is in control using two sigma limits. No. of defects
1.
Construct the appropriate control chart for the 11 observations, and determine if the process is in control using two sigma limits. No. of defects per unit for the observations are: 9, 7, 4, 6, 4, 8, 11, 4, 6, 6, 9.
a.
2 observations out of control
b.
Under control
c.
3 observations out of control
d.
1 observation out of control
2.
Which of the following is not written in the standard form of a linear programming problem constraint?
a.
1A + 2B 3
b.
1A + 2B = 3
c.
1A + 2B 3
d.
2A 3B
e.
1A + 2B + 3C + 4D 5