Question: 1 ) Construct the CPM network described by the following set of activities, computer the length of each patch in the network, and indicate the

1) Construct the CPM network described by the following set of activities, computer the length
of each patch in the network, and indicate the critical path.
Activity Time (months)
1!24 Activity Preceed Act. Time
1!37 A -10
2!48 B A8
2!53 C A5
3!59 D B6
4!55 E D8
4!62 F C7
5!66 G E,F 4
3!65 H F2
I F3
J H,I 3
K J,G 2