Question: 1 . Create a digraph for the following set of tasks: Task Time required Tasks that must be completed first A 3 B 4 C

1. Create a digraph for the following set of tasks:
Task Time required Tasks that must be
completed first
A 3
B 4
C 7
D 6 A, B
E 5 B
F 5 D, E
G 4 E