Question: 1. Create a simple project of 8-10 tasks. Create a task list with projected task duration. Assume a project start date and build a
1. Create a simple project of 8-10 tasks. Create a task list with projected task duration. Assume a project start date and build a Gantt chart to illustrate the project schedule and associated task dependencies. 2. Provide an explanation of "critical path". How does a project manager use the critical path to manage project schedule? 3. Examine the following network diagram. List all possible sequences (chain/path) of activities and define the total duration for each path. (Hint: there are 5 possible paths). Note: Tasks are identified as "a" through "i" and "dummy". What is the critical path? 3 8 a 2 10 20 12 13 - Kuunp
Step by Step Solution
3.48 Rating (141 Votes )
There are 3 Steps involved in it
1 Activity Predecessor Expected duration 4 7 3 8 4 3 2 6 3 7 3 2 8 456 5 Precedence Diagram ... View full answer