Question: (1) De termine the critical path and the expected project duration Critical Path Expected Project Duration A-C-FI 4+7 +5 +6 =22 A-DGI 4+11+3+6 =24 B-EH

(1) De termine the critical path and the expected
(1) De termine the critical path and the expected project duration Critical Path Expected Project Duration A-C-FI 4+7 +5 +6 =22 A-DGI 4+11+3+6 =24 B-EH 8+11+9=28 Expected Duration=28 (2) De termine the following quantities for each activity: the earliest start time, the latest start time, the earliest finish time and the latest finish time and the slack time. C (7) F (5) 7 A (4) +16) B (11) G437 5 H (9) B (8) 3 E (11) 6