Question: 1- Determine the project duration and the critical path manual and use MS. Project for the following project. 2- Develop the AOA network of
1- Determine the project duration and the critical path manual and use MS. Project for the following project. 2- Develop the AOA network of the project. (Productivity) 50 (m/day) 15 (m/day) 20 (m/day) 15 (No/day) 25 (m/day) 150 (m/day) 150 (No /day) 1,000 (m/day) 15 (m/day) 15 (No /day) (Quantity) 400 m 300 m 120 m 90 No 500 m 600 m 900 No 6,000 m 150 m 450 No -(Lag) day - " 2 NOOT 10 0 7 5 8 3 10 (Logical (Predecessor) (Activity) Relation) - - FS SS FF FS SS FS SS FS SS - B C D A F A C E H A B C D E F IO G 1 J
Step by Step Solution
There are 3 Steps involved in it
1 Project Duration and Critical Path Using MS Project the project duration is 25 days a... View full answer
Get step-by-step solutions from verified subject matter experts
