Question: 1 . Develop 3 sigma level process control charts for monitoring weight of firewood in bags. An inspector performed sampling over 4 weeks of time

1. Develop 3 sigma level process control charts for monitoring weight of firewood in bags. An inspector performed sampling over 4 weeks of time frame. Each time, 4 observations were made as below. Calculate and show values for UCL, CL, and LCL using the factors provided in below table (do not calculate these values using the raw data). Draw variable control charts (mean and range). Discuss your conclusion. You can draw using Excel or hand draw and scan.
week 1 week 2 week 3 week 4
20282030
24302820
22212624
26242626