Question: 1. Draw a network diagram 2. Find the minimum time of completion of the project Example Predecessor Activity A B A DB F,GEH Duration (Days)

1. Draw a network diagram

2. Find the minimum time of completion of the project

1. Draw a network diagram 2. Find the minimum

Example

1. Draw a network diagram 2. Find the minimum

Predecessor Activity A B A DB F,GEH Duration (Days) 8 10 8 10 16 17 18 14 9 Activity Predecessor Duration (weeks) A 5 B A 4 A 5 D B 6 E 3 F DE 4 ANSWER ES -Earliest start EF - Earliest finish LS- Latest start LF =Latest finish ulun B 4 9 9 9 9 D 6 15 15 0 0 A 5 5 5 15 15 F 4 19 19 U 5 7 5 10 12 10 12 E 3 13 15