Question: 1 - Draw a network diagram for this project 2 - . Identify all paths through the network diagram. Identify which path you expect to

1-Draw a network diagram for this project
2-. Identify all paths through the network diagram. Identify which path you expect to be the critical
path and its expected completion time?
3-Which paths are most likely to threaten this path in terms of becoming critical?
4- Simulate the completion of this project 1,000 times assuming that activity times follow a PERT
distribution.
5-Estimate the mean and standard deviation of the project completion time and the project cost.
6- Develop histograms for both the project completion time and the cost to complete the project.
What do these histograms tell you?
7- Using the results of your simulation analysis,
A-calculate the probability that the project can be completed within 30 months.
B-What is the probability that the project will take longer than 40 months?
C- What is the probability that the project will take between 30 and 40 months?
D- What is the probability the project will cost $5.1 million or less to complete?
E-The probability the project will cost between $5 and $6 million to complete?
 1-Draw a network diagram for this project 2-. Identify all paths

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!