Question: 1- Draw a Project network for the customer order project of the Air Control Company. The project information given below. Compute the early and late

1- Draw a Project network for the customer order project of the Air Control Company. The project information given below. Compute the early and late activity times and the slack times. Identify critical path.

IDDescriptionPredecessorTime

AOrder ReviewNone 2

BOrder Standard parts A3

CProduce Standard parts A10

DDesign Custom Parts A13

ESoftware Development A18

FManufacture custom Hardware C, D15

GAssembleB, F10

HTestE, G5