Question: 1. Draw the activity chart and identify the critical path/activities based on te aform of AON showing ES, EF, LS, LF, Te, and Slack 2.
1. Draw the activity chart and identify the critical path/activities based on te aform of AON showing ES, EF, LS, LF, Te, and Slack
2. What would be the probability of reducing the project length by 1 day? 3. What would be the probability of increasing the project legth by 1 day?
Achily Predecessor Es EF LF Slack (a tumto) None 1219 3 5 Te None 3 2 8 5 Tu T3 3 415 u S16 113 7 Ts T6 72 Ts 7 10/19 11 T TA Tu, To 8 16 18 15 T8 Ta 113153 19 ToStep by Step Solution