Question: 1 . Draw the project network and list the earliest start ( ES ) , earliest finish ( EF ) , latest start ( LS

1. Draw the project network and list the earliest start (ES), earliest finish (EF), latest start (LS)
and latest finish (LF) for each task
2. List the tasks on the critical path
3. What is the expected project duration in weeks?
4. What is the slack for each activity?
A: B: C: D: E: F: G:
OPS 3880 AP5
5. The project needs to be crashed by 2 weeks. What are the activities crashed to achieve the 2
week crash at lowest cost? List the new duration of each crashed task and any associated
crash costs
Activity Duration Crash Cost
A
B
C
D
E
F
G
6. Draw the NEW project network and list the earliest start (ES), earliest finish (EF), latest start
(LS) and latest finish (LF) for each task
7. List the tasks on the critical path
 1. Draw the project network and list the earliest start (ES),

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!