Question: 1. During a software rollout, the project team gathers performance data, produces key metrics, and shares the findings with stakeholders. They also examine differences between
1. During a software rollout, the project team gathers performance data, produces key metrics, and shares the findings with stakeholders. They also examine differences between planned and actual performance and propose solutions to address delays. Which of the following statements are true? (Please indicate all that apply. Incorrect answers will be negatively marked.)Select one or more: Controlling ensures that performance measures are produced and shared Monitoring requires evaluating alternatives and implementing solutions Monitoring involves collecting and reporting performance information Monitoring focuses solely on approving deliverables Controlling includes analysing variances and recommending corrective actions