Question: (1) etermine by how many weeks activity G can be delayed by without affecting the overall project duration (9) etermine by how many weeks activity

(1) etermine by how many weeks activity "G" can

(1) etermine by how many weeks activity "G" can be delayed by without affecting the overall project duration (9) etermine by how many weeks activity "M" can be delayed by without affecting the overall project duration (h) Explain the implications of the critical path that you have calculated above. Activity Predecessors Weeks A A B B DC B D E F G H I 1 J L M N 2 3 4 3 3 4 4 5 8 3 4 3 2 3 D FE GH H JK J I,M,L