Question: 1- Find the project duration. * a. 18 b. 22 c. 20 d. None of the above 2- Calculate the activity crashing costs of A.

1- Find the project duration. *
a. 18
b. 22
c. 20
d. None of the above
2- Calculate the activity crashing costs of A. *
a. 125
b. 150
c. 80
d. None of the above
3- How many time does activity E be crashed *
a. 1 time
b. 2 times
c. 3 times
d. None of the above
4- If you need to crash the project by one week. Which activity would you crash? *
a. A
b. B
c. C
d. G
5- Crash the project by another one week. Which activity would you crash? *
a. A
b. B
c. C
d. G
6- Crash the project by another one week. Which activity would you crash? *
a. A
b. B & E
c. E & D
d. G
7- Crash the project by another week. Which activity would you crash? *
a. A
b. B & E
c. E & f
d. G
8- What is the additional cost of the project after crashing? *
a. $5000
b. $5700
c. $5775
d. None of the above
plz solve all 8 questions. its urgent
A project has the following data: Activity Predecessor Normal Crashing Normal Crashing Time Time Cost cost A 5 1100 1225 B A 6 4 500 600 A 5 3 700 800 D B 5 4 600 750 E 6 5 1000 1050 F D 2 1 600 1000 F, E 2 1 1000 1800Step by Step Solution