Question: 1: Find /Using the table below: Develop separate schedules using the SPT and EDD rules. Compare the two schedules. Which rule gives better schedule and
1:
Find /Using the table below:
- Develop separate schedules using the SPT and EDD rules.
- Compare the two schedules. Which rule gives better schedule and WHY?
| Parts | Hours Since Order Arrived (hours) | Processing Time, Including Setup (hours) | Scheduled customer pickup time (hours) |
| A | 3 | 6 | 8 |
| B | 9 | 3 | 15 |
| C | 8 | 8 | 12 |
| D | 5 | 2 | 20 |
| E | 15 | 4 | 10 |
2:
A company wishes to improve its layout. The following layout shows the current layout:
Current layout
| A | C | E | G |
| B | D | F | H |
The following table shows the closeness factors (W) between departments.
- Use trial and error to find a better layout.
- How much better is your layout than the current layout in terms of the WD score?
| Departments | A | B | C | D | E | F | G | H |
| A | - | 7 | 1 | 5 |
|
|
| 9 |
| B |
| - | 3 | 8 |
| 3 |
|
|
| C |
|
| - | 4 |
| 9 |
|
|
| D |
|
|
| - | 7 | 8 |
| 2 |
| E |
|
|
|
| - |
| 3 |
|
| F |
|
|
|
|
| - |
| 8 |
| G |
|
|
|
|
|
| - | 7 |
| H |
|
|
|
|
|
|
| - |