Question: 1. Flow Process Chart: Summary Present Total # Time Proposed Total # Time Difference Total # Time Operations (O) Transportations () Inspections () Delays (D)
1. Flow Process Chart:
| Summary | Present Total # Time | Proposed Total # Time | Difference Total # Time | |||
| Operations (O) | ||||||
| Transportations () | ||||||
| Inspections () | ||||||
| Delays (D) | ||||||
| Storage () |
| Distance Traveled | Ft. | Ft. | Ft. |
Details of Present Method
| Present Method | Operation/ Transportation /Inspection/ Delay/Storage | Distance (feet) | Time (minutes) |
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D |
Details of Proposed Method
| Proposed Method | Operation/ Transportation /Inspection/ Delay/Storage | Distance (feet) | Time (minutes) |
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D | |||
| O D |
Complete one flow process chart for the current procedure for handling mail:
1. Sort mail by addressee. (5 minutes) 2. Deliver mail to addressees. (200' round trip, 20 minutes) 3. Open remaining mail. (5 minutes) 4. Read mail to see who should answer it. (average 2 hours -convert hours to minutes!) 5. Write name of responsible staff member on top of mail document. (average 20 minutes) 6. Sort mail by name of responsible staff member. (average 5 minutes) 7. Deliver mail to addressees. (200' round trip, 20 minutes)
Make sure to fill in the summary at the top of the page. Note the difference between the present and proposed procedure.