Question: 1 ) For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If

1) For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If the early finish times of an activity's predecessors were 85,70 and 55, then this time would be the largest of these three early finish times or 85.
A) late finish
B) early finish
Clate start
D) carly start
E) free slack
2) Which of the following is typically the responsibility of a project manager?
A) Coordinating the actions of the team
members
8) All of these are typical responsibilities C) Meeting budget requirements
0) Meeting performance specifications
E) Meeting schedule requirements
3) Choosing to move a concert indoors to eliminate the threat of had weather is an example of
arisk
A) escalating
8) transferring
C) mitigating D) avoiding
E) retaining1) For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If the early finish times of an activity's predecessors were 85,70 and 55, then this time would be the largest of these three early finish times or 85.
A) late finish
B) early finish
Clate start
D) carly start
E) free slack
2) Which of the following is typically the responsibility of a project manager?
A) Coordinating the actions of the team
members
8) All of these are typical responsibilities C) Meeting budget requirements
0) Meeting performance specifications
E) Meeting schedule requirements
3) Choosing to move a concert indoors to eliminate the threat of had weather is an example of
arisk
A) escalating
8) transferring
C) mitigating D) avoiding
E) retaining1) For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If the early finish times of an activity's predecessors were 85,70 and 55, then this time would be the largest of these three early finish times or 85.
A) late finish
B) early finish
Clate start
D) carly start
E) free slack
2) Which of the following is typically the responsibility of a project manager?
A) Coordinating the actions of the team
members
8) All of these are typical responsibilities C) Meeting budget requirements
0) Meeting performance specifications
E) Meeting schedule requirements
3) Choosing to move a concert indoors to eliminate the threat of had weather is an example of
arisk
A) escalating
8) transferring
C) mitigating D) avoiding
E) retaining

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!