Question: 1 ) For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If
For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If the early finish times of an activity's predecessors were and then this time would be the largest of these three early finish times or
A late finish
B early finish
Clate start
D carly start
E free slack
Which of the following is typically the responsibility of a project manager?
A Coordinating the actions of the team
members
All of these are typical responsibilities C Meeting budget requirements
Meeting performance specifications
E Meeting schedule requirements
Choosing to move a concert indoors to eliminate the threat of had weather is an example of
arisk
A escalating
transferring
C mitigating D avoiding
E retaining For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If the early finish times of an activity's predecessors were and then this time would be the largest of these three early finish times or
A late finish
B early finish
Clate start
D carly start
E free slack
Which of the following is typically the responsibility of a project manager?
A Coordinating the actions of the team
members
All of these are typical responsibilities C Meeting budget requirements
Meeting performance specifications
E Meeting schedule requirements
Choosing to move a concert indoors to eliminate the threat of had weather is an example of
arisk
A escalating
transferring
C mitigating D avoiding
E retaining For any activity that has one or more predecessors, the time is always the largest early finish of any of its predecessors If the early finish times of an activity's predecessors were and then this time would be the largest of these three early finish times or
A late finish
B early finish
Clate start
D carly start
E free slack
Which of the following is typically the responsibility of a project manager?
A Coordinating the actions of the team
members
All of these are typical responsibilities C Meeting budget requirements
Meeting performance specifications
E Meeting schedule requirements
Choosing to move a concert indoors to eliminate the threat of had weather is an example of
arisk
A escalating
transferring
C mitigating D avoiding
E retaining
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock