Question: 1. For the following information on a project, develop a project network. Determine the critical path. Calculate Early Start, Early Finish, Late Start, Late Finish
1. For the following information on a project, develop a project network. Determine the critical path. Calculate Early Start, Early Finish, Late Start, Late Finish and Slack time.
| Activity | Duration | Preceding Activity | Resource Required |
| A | 2 | ---------- | 2 |
| B | 3 | A | 2 |
| C | 2 | B | 2 |
| D | 4 | B | 1 |
| E | 5 | B | 2 |
| F | 2 | C & D | 2 |
| G | 1 | E &F | 1 |
2. Develop a resource schedule to see if it possible for project to finish in time with resource constrained of 2 engineers working on the project.