Question: 1. For the following information on a project, develop a project network. Determine the critical path. Calculate Early Start, Early Finish, Late Start, Late Finish

1. For the following information on a project, develop a project network. Determine the critical path. Calculate Early Start, Early Finish, Late Start, Late Finish and Slack time.

Activity

Duration

Preceding Activity

Resource Required

A

2

----------

2

B

3

A

2

C

2

B

2

D

4

B

1

E

5

B

2

F

2

C & D

2

G

1

E &F

1

2. Develop a resource schedule to see if it possible for project to finish in time with resource constrained of 2 engineers working on the project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!