Question: 1) Formulate Setup Time Column. 2) Update Start Time Formula 3)Try to find the best sequence. 4)Try to find Total Tardiness < 90 Job

1) Formulate Setup Time Column. 2) Update Start Time Formula 3)Try to  find the best sequence. 4)Try to find Total Tardiness < 90 Job

1) Formulate Setup Time Column. 2) Update Start Time Formula 3)Try to find the best sequence. 4)Try to find Total Tardiness < 90 Job ID Ready Time Process Time Due Da 1 4 8 89 2 21 8 74 3 14 2 88 4 22 5 88 5 0 7 62 9 19 8 59 7 1 7 72 00 8 25 00 8 84 6 22 3 50 10 24 4 55 11 16 8 90 12 4 3 62 13 11 2 78 14 8 3 55 15 1 2 69

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!