Question: 1 . Given: PERT Project Data Activity Immediate Predecessor ( s ) Optimistic time Most Likely time Pessimistic time A - 1 2 4 B

1. Given: PERT Project Data
Activity
Immediate Predecessor(s)
Optimistic time
Most Likely time
Pessimistic time
A
-
1
2
4
B
-
5
6
7
C
-
2
4
5
D
A
1
3
4
E
C
4
5
7
F
A
3
4
5
G
B,D,E
1
2
3
Find the probability of completing the project in 12 weeks. In 10-13weeks. Use upper and lower limits.