Question: 1. Given the following activity network: Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the earliest start

1. Given the following activity network:

Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the earliest start time of A3?

A) 13 weeks

B) 7 weeks

C) 10 weeks

Plz provide the correct answer out of this option below thanks ||