Question: 1. Given the following information about 7/1/L scheduling problem: 7 Job PI d) 1 6 20 2 4 17 3 8 19 4 3 23

1. Given the following information about 7/1/L
1. Given the following information about 7/1/L scheduling problem: 7 Job PI d) 1 6 20 2 4 17 3 8 19 4 3 23 5 2 29 7 33 26 (a) What basic sequencing rule would be use for this problem? (b) Write here an optimal sequence for this problem based on the rule you specified in part (a). (C) What is the value of your performance measure for the sequence of part (b)