Question: 1 . Given the project information below, answer the following questions: Activity Predecessor Optimistic Time ( a ) Most Likely Time ( m ) Pessimistic

1. Given the project information below, answer the following questions:
Activity Predecessor Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) Expected Time (Te) Variance
A None 31227
B None 82026
C A 4716
D A, B 273045
E C,D 101316
Using PERT method and based on expected time (Te) for each activity, determine the expected project duration (rounded to whole numbers).
2. C7Q2 is based on the same information as presented for C7Q1
Given the project information below, answer the following questions:
Activity Predecessor OptimisticTime (a) MostLikely Time (m) PessimisticTime (b) ExpectedTime (Te) Variance
A None 31227
B None 82026
C A 4716
D A, B 273045
E C,D 101316
Question C7Q2:
What is the probability of completing the project in 58 periods? Fill a decimal value in the blank below (Note: rounded to 4 decimals

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!