Question: 1 . Given the project information below, answer the following questions: Activity Predecessor Optimistic Time ( a ) Most Likely Time ( m ) Pessimistic
Given the project information below, answer the following questions:
Activity Predecessor Optimistic Time a Most Likely Time m Pessimistic Time b Expected Time Te Variance
A None
B None
C A
D A B
E CD
Using PERT method and based on expected time Te for each activity, determine the expected project duration rounded to whole numbers
CQ is based on the same information as presented for CQ
Given the project information below, answer the following questions:
Activity Predecessor OptimisticTime a MostLikely Time m PessimisticTime b ExpectedTime Te Variance
A None
B None
C A
D A B
E CD
Question CQ:
What is the probability of completing the project in periods? Fill a decimal value in the blank below Note: rounded to decimals
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
