Question: 1. How is the default timescale in Microsoft Project 2016 arranged? A. By months. B. By weeks and days. C. By minutes and seconds. D.

1. How is the default timescale in Microsoft Project 2016 arranged? A. By months. B. By weeks and days. C. By minutes and seconds. D. By years. 2. What is the default view (screen) in Microsoft Project? A. The Calendar view B. The Gantt Chart view. C. The Resource Usage view D. The Network Diagram view 3. What criteria do you use when entering tasks in Microsoft Project? A. Enter them in order of cost (high cost first). B. Enter them in order of occurrence C. Enter them in alphabetical order D. Enter them in order of importance 4. What is the default calendar in Microsoft Project? A. The Project calendar B. The Flexible calendar. C. The 24 Hours calendar D. The Night Shift calendar. 5. Which element of the triple constraint typically can't be changed for a surprise 50th-birthday-party project? A. Cost. B. Time C. Scope. D. Stakeholders
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts