Question: 1 - How long will it take a crawler dozer with straight blade to move 6 , 7 0 0 m 3 for 1 5

1-How long will it take a crawler dozer with straight blade to move 6,700m3 for 150 meters?
The ideal production for 150m distance is 320LCM. Ideal production values are based on a
soil density of 2,300kgLCM.
Grade -2%(down grade correction 1.07).
Dry clay, 1,950kgLCM.
Operator of average skill (operator skill 0.75).
The operating time is 50-min? hour.
2-A track-type tractor whose weight is 15 tons has a drawbar pull of 5,685kg when operated on
a level road with a rolling resistance of 110kgton. If the tractor is operated on a level road
with 180kg? ton rolling resistance, what will be the effective drawbar pull?
3-A wheel tractor scraper is used on a road project. When the project begins, the scraper will
experience high rolling and grade resistance at one work area. The rimpull required to
maneuver in this work area is 42,000kg. In fully loaded condition, 52% of the total vehicle
weight is on the drive wheels. The fully loaded vehicle weight is 230,880kg. What minimum
value of coefficient of traction between the scraper wheels and the traveling surface is needed
to maintain maximum possible travel speed?
4-A contractor proposes to use scrapers on an embankment job. The performance characteristics
of the machines are shown in the figures. The scrapers have a rated struck capacity of 14-cy.
Operating weight empty is 69,000lb. The weight distribution of the scraper when loaded is
53% on the drive wheels. The contractor believes that the average scraper load will be 15.2
BCY. The haul from the excavation area is a uniform adverse gradient of 5.0% with a rolling
resistance of 60Ibton. The material to be excavated and transported is common earth with a
bank unit weight of 3,200IbBCY.
a. Calculate the maximum travel speeds that can be expected. Equivalent Grade %=
rolling resistance factor (lb/ton)/20.
b. If the job is at elevation 12,500ft, what will be the operating speeds when consideration
of the nonstandard barometric pressure is included in the analysis? For operating at an
altitude of 12,500 ft, the manufacturer has reported that these scrapers, which have
turbocharger engines, can deliver 82% of rated horsepower.
1 - How long will it take a crawler dozer with

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!