Question: 1. how much should each activity be reduced by in weeks? 2. what is the total crashing cost? The following is a table of activities
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week Suppose that Rafay is only given 7 weeks (instead of 10 ) to complete the project. By how many weeks should each activity be crashed in order to meet the deadline? Assume that you can crash an activity down to 0 weeks duration