Question: 1.) Identify the critical path. a) A-B-D-F b) A-C-E-F c) A-C-D-F d) A-B-E-F 2.) What is the normal project length? a) 30 b) 28 c)

1.) Identify the critical path.
a) A-B-D-F
b) A-C-E-F
c) A-C-D-F
d) A-B-E-F
2.) What is the normal project length?
a) 30
b) 28
c) 24
d) 25
3.)What is the project length if all activities are crashed to their minimum?
a) 24
b) 20
c) 19
d) 23
4.Bragg's loses $3,600 in profit per week for every week the bakery is not completed. How many weeks will the project take if we are willing to pay crashing cost as long as it is less than $3,600?
a) 28 weeks
b) 27 weeks
c) 29 weeks
d) 26 weeks
NORMAL CRASH TIME TIME EXPEDITING ACTIVITYPREDECESSOR(WEEKS)(WEEKS)COST/WEEK 3,500 A 6 5 $ 3,900 B A 5 3 4,200 A . 11 8 2,200 D B, C 8 7 2,500 3 2 4,800 D, E 5 4Step by Step Solution